Question 248

The Business Development Director is the senior user. She has agreed a plan for post-project benefit reviews as part of the 'evaluate the project' activity.

Is this an appropriate application of the 'closing a project' process, and why?

    Correct Answer: B

    The 'closing a project' process should include an assessment of the benefits achieved compared with those defined in the business case. This ensures that the project has delivered the expected outcomes and justifies the investment made. The role of the senior user is to ensure that the products are fit for purpose and that the benefits are realized. Planning post-project benefit reviews aligns with this objective, making option B the most appropriate answer.

Discussion
ravi_awsOption: B

B) Yes, because there should be an assessment of the benefits achieved compared with those defined in the business case is the correct answer.