Question 62

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

    Correct Answer: B

    A cross-functional characteristic of a project means that it involves different departments or expertise. This often reflects varying perspectives and motivations from different stakeholders, including customers and suppliers. As these stakeholders come from different functional areas, their perspectives and interests may vary, which is why 'Cross-functional' is the correct choice.

Discussion
NavipatriOption: B

Correct B. It’s one of the characteristics of the project: temporary, change, cross-functional, unique and uncertainty