PRINCE2-Practitioner Exam - Question 219


The Training Development Manager is the senior supplier. Towards the end of stage 3, the Training Development Manager selected a course developer to deliver the work package for the 'finalized materials'. As a result, the project manager asked the course developer to produce a plan for this work.

Is this an appropriate application of the 'organization' theme, and why?

Show Answer
Correct Answer: B

The plan produced by the course developer demonstrates how the product, in this case, the 'finalized materials', will be delivered at the 'delivering' level of management. This is aligned with the responsibilities at this level, where detailed plans are created to guide the execution of work packages.

Discussion

1 comment
Sign in to comment
ravi_awsOption: B
Oct 6, 2023

Yes, because the plan demonstrates how the product will be delivered at the 'delivering' level of management