The Training Development Manager is the senior supplier. Towards the end of stage 3, the Training Development Manager selected a course developer to deliver the work package for the 'finalized materials'. As a result, the project manager asked the course developer to produce a plan for this work.
Is this an appropriate application of the 'organization' theme, and why?