Question 53

How many roles make up the Project Board?

    Correct Answer: C

    The Project Board in a project management context typically consists of three roles: the Executive, the Senior User, and the Senior Supplier. These roles provide comprehensive oversight and guidance for the project's progress, ensuring that business interests, user requirements, and supplier capabilities are all represented.

Discussion
FireyOption: C

The Project Board consists of the Executive , the Senior User and the Senior Supplier.

tarunkumarsatpathy

Business User Supplier Roles