PRINCE2-Practitioner Exam - Question 243


The delivery team has produced the amended course booking procedures' produced in accordance with the requirements documented in the appropriator work package. Which role should review the procedures as part of the 'execute a work package' activity to ensure that they meet the quality criteria included in the product description?

Show Answer
Correct Answer: D

The role responsible for reviewing the procedures as part of the 'execute a work package' activity to ensure that they meet the quality criteria included in the product description is 'Project assurance'. Project assurance is responsible for providing independent assurance that the project is being conducted properly and that quality processes are being followed and met.

Discussion

1 comment
Sign in to comment
ravi_awsOption: D
Oct 7, 2023

D. Project assurance