In the quality management approach, it has been specified that the quality register will be part of an integrated project register for risks, issues and lessons. It will be stored in an electronic spreadsheet on a shared drive so that it can be accessed by any project team member. Each team member will update the quality register with their own quality activities, when they believe that progress has been made.
Is this an appropriate application of the quality register, and why?