PRINCE2-Practitioner Exam - Question 13


Which of the following statements is FALSE regarding the Continued Business Justification?

Show Answer
Correct Answer: A

The justification for the project must not necessarily remain the same throughout the project. It can change as the project progresses. The crucial point is that the justification should remain valid. Therefore, the statement that the justification must remain the same throughout the project is false.

Discussion

13 comments
Sign in to comment
timedoutOption: C
Oct 12, 2021

For below reference is 3.1

Stu_Dent
Apr 13, 2024

The references help the most as they can be verified by going back to the book and checking.

johnzoidsOption: A
Jul 17, 2020

A is the answer

CilubaOption: A
Dec 28, 2020

Should be A

timedoutOption: A
Nov 14, 2021

Its A.. I missed False... oops

ameyaenggOption: A
Sep 17, 2022

A is the answer

georgio1974Option: A
Aug 2, 2023

agree A

timedoutOption: B
Oct 12, 2021

D - Justification can change, but must remain valid. If a project can no longer be justified it should be stopped.

timedoutOption: B
Oct 12, 2021

Or is it B... Last miss spelt word is "valid"... So B and D?

MortenCOption: A
Feb 17, 2023

A is the answer

TonyKaraOption: A
Apr 17, 2023

A is most definitely the answer.

PieroBeOption: A
Jul 24, 2023

The justification of a project may change during its development. What is important is to find a valid justification. So it is definitely A.

ShiroKurtiaOption: A
Aug 2, 2023

Should be A

ManikRoyOption: B
Sep 17, 2023

Its definitely B i.e. the justification must remain valid while it may change.

Abu_Elias
Sep 22, 2023

The question is about the FALSE statement. Correct answer is A.

ManikRoy
Sep 25, 2023

Agreed, thanks for notifying.