Which product should show that the staff photo sessions were disruptive to the Engineering Department as they had been scheduled during peak work times without consultation with the Engineering Manager?
Which product should show that the staff photo sessions were disruptive to the Engineering Department as they had been scheduled during peak work times without consultation with the Engineering Manager?
The correct choice to document that the staff photo sessions were disruptive to the Engineering Department due to poor scheduling without the Engineering Manager's input would be the Lessons Report. The Lessons Report is designed to record such lessons learned and issues encountered during a project so that they can be avoided in future activities. Including this information in the Lessons Report ensures that similar disruptions are mitigated in future projects through better planning and consultation.
While the other options could potentially reference this issue, the Lessons Report is the document purpose-built to record this type of lesson learned for future improvement. Therefore, B is the correct choice to document that the staff photo sessions were disruptive to Engineering because of suboptimal scheduling without input from the Engineering Manager. The details should be captured in the Lessons Report to inform scheduling on future projects.