Question 14

Which of the following activities is NOT an action of preparing for planned closure?

    Correct Answer: B

    Preparing for planned closure involves tasks that ensure everything is completed and documented according to the project plan. Updating the project plan with actuals, requesting a product status account, and confirming that the project has delivered what is defined in the Project Product Description are all tasks that contribute to this process. However, simply updating the Project Management Team does not directly relate to the completion and documentation of project activities required for formal closure; it is more of an ongoing communication task.

Discussion
PrincessOfHessOption: B

It is B: 20.4.1