Question 47

Which statement about timeboxes is CORRECT?

    Correct Answer: C

    A timebox is a fixed period within which specific tasks are to be completed. In project management, a timebox can indeed contain another timebox, as larger projects or stages might be broken down into smaller timeboxes for better management and control. This helps in maintaining structure and ensuring that each phase of a project remains on schedule.

Discussion
DjtomipOption: C

c is fine

GeproOption: B

Answer C is definitly wrong. As per 1.2.2 of Axelos' official PRINCE Agile Book "... Higher-level timeboxes act as aggregated timeboxes and contain lower-level timeboxes (e.g. stages)."