PRINCE2-Practitioner Exam - Question 192


The team member collating the list of customers has now forecast that it will NOT be complete by the end of this stage as originally planned, due to a number of new prospective customers' details not yet being available. What action should the team member take?

Show Answer
Correct Answer: D

The correct action for the team member to take is to raise an issue to inform the Project Manager. When a forecast indicates that a deliverable will not be completed as planned, it is essential to immediately inform the Project Manager so that corrective actions can be taken. This allows the Project Manager to assess the situation, make necessary adjustments, and implement any required measures to address the delay.