PRINCE2-Practitioner Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Exam - Question 129


DRAG DROP -

CONTROLLING A STAGE -

Here are three activities that take place during the 'controlling a stage' process. Which role (A-F) should carry out each activity? Choose only one role for each action. Each role can be used once, more than once, or not at all.

Select and Place:

Show Answer
Correct Answer:

Discussion

1 comment
Sign in to comment
ravi_aws
Oct 10, 2023

1. Project manager 2.Project Assurance 3.Team manager