Which 2 statements should be recorded under the Major risks heading?
Which 2 statements should be recorded under the Major risks heading?
The significant risks that should be recorded under the Major risks heading include the potential for not finding a suitable service provider due to market conditions, which could lead to premature closure of the project and hinder successful implementation; and the possibility of staff resistance to outsourcing due to employment contract changes, which would make it difficult to transfer staff to the selected service provider. Other options mention issues that are either less impactful or more certain to happen, hence not fitting the criteria of major risks.
I also believe A & B are the best answers. C is a risk but not for the customer organization D is not a risk as it'll happen for sure E sounds more like a concern than a risk
I believe A & B are best answers. D is not a Risk at all. As it is something that definitely will happen.
A. Due to market conditions a suitable service provider may not be found, possibly leading to premature closure of the project. This is a significant risk that could prevent the project from being implemented as planned. B. Owing to employment contract changes staff may resist outsourcing, which would make it difficult to transfer staff to the selected service provider. This is another major risk that could hinder the successful implementation of the project.