What is the definition of a project outcome?

Show Answer
Correct Answer: C

A project outcome is the result of the change derived from using the project's outputs. This definition accurately portrays how outcomes reflect the real-world effects or impacts that occur as a consequence of implementing the project's deliverables.

Discussion

6 comments
Sign in to comment
NugiOption: C
Jun 30, 2021

Answer is C: outcome The result of change, normally affecting real-world behaviour and/or circumstances. Outcomes are desired when a change is conceived. They are achieved as a result of the activities undertaken to effect the change.

peppeOption: C
Oct 15, 2021

C: "outcome The result of change, normally affecting real-world behaviour and/or circumstances. Outcomes are desired when a change is conceived. They are achieved as a result of the activities undertaken to effect the change.

Ashu_1Option: D
May 24, 2021

Correct answer is D. Option C is the result of change which have been derived from project outcome. So how it can be a project's outcome?

steunetOption: C
Aug 24, 2021

C without doubts: the outcome can be understood as a change caused by using the project’s output

PepiGOption: C
Dec 6, 2021

The correct answer is C and not D. The definition you presented is not quite accurate, it's a small detail that makes the difference. The OUTCOME is the result of a change results from project's OUTPUT (not outcome).

a2d1fd1Option: C
Apr 4, 2024

the result of a change is implemented to achieve outcomes- the definition of an outcome.