Question 47

HOTSPOT -

The project has a cost tolerance of +5% I ֲ·5%, of which stage 2 has a tolerance of +ֲ£45k 1-ֲ£45k.

Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Hot Area:

    Correct Answer:

Discussion
PrincessOfHess

The stage plan shput be prepared for the next management phase. (19.4.1)