PRINCE2-Practitioner Edition 6 Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Edition 6 Exam - Question 31


At the end of stage 2, an external consultant responsible for developing the 'e-learning course', was appointed to the project board as a senior supplier. The stage

3 plan identifies the consultant as a reviewer of the 'e-learning course'. When preparing for a quality review of the 'e-learning course', the consultant found 15 possible errors. The consultant then documented these possible errors in the quality register.

Is this an appropriate activity when preparing for a quality review, and why?

Show Answer
Correct Answer: C

No, because possible errors that are found when preparing for a quality review should be documented on a question list. During the preparation phase of a quality review, any potential issues or errors should be recorded on a question list to be addressed in the review meeting, rather than updating the quality register, which is done after the review activities are completed.

Discussion

6 comments
Sign in to comment
Ciluba
Dec 28, 2020

C should be correct Page 91, Section 8.4.4 Unless some background information are missing. Who said the review activities are completed?

Chivasa
Oct 24, 2023

The answer C clearly states that quality review activities are completed though.

Chivasa
Oct 24, 2023

I was confusing B with C, my mistake

Chivasa
Oct 24, 2023

I was confusing B with C, my mistake

PieroBeOption: D
Jul 24, 2023

The Senior Supplier is the (ultimate) responsible for products to be developed in the project, so he cannot act as a reviewer of these products because it generates a conflict of interests.

ManikRoyOption: C
Sep 25, 2023

Refer to 8.4.4 Preparing For review Submit a question list to the chair and presenter ahead of the review (reviewers).

ManikRoy
Dec 13, 2023

Correcting my previous answer. Correct answer is option D - senior supplier can not be made reviewer as the supplier is responsible for developing the product and thus the quality review won't work.

Trikuta_Kaira
Aug 22, 2022

No, because the senior supplier should not be identified as a reviewer as part of the quality review technique.

MortenC
Feb 8, 2023

The question is about activity not role.....ie B

ravi_aws
Sep 30, 2023

Therefore, the answer is B. Yes, because the quality reviewers should update the quality register as quality review activities are completed. The quality reviewers are responsible for updating the quality register as quality review activities are completed

ManikRoy
Oct 4, 2023

The question mentions 'While preparing for the quality review'