During the initiation stage the Corporate Quality Manager advised the project manager that ABC Company's risk management tool should be used by the project.
The project manager prefers an alternative tool and has documented this in the projects risk management approach which has been approved by the project board.
Is this an appropriate application of the risk management approach, and why?