PRINCE2-Practitioner Exam - Question 135


DRAG DROP -

PLANS -

Here are three events to managing plans for the project.

In which management product (A-E) should the result of each event be recorded?

Choose only one product for each event. Each product can be used once, more than once or not at all.

Select and Place:

Show Answer
Correct Answer:

Discussion

3 comments
Sign in to comment
Duribaci
Mar 2, 2023

What about 1st and 2nd choices? I thing it is not correct..

ravi_aws
Oct 4, 2023

Team Plan Stage Plan Exception Plan

ManikRoy
Oct 9, 2023

1. Work package 2. Stage Plan 3. Exception Plan

ravi_aws
Oct 10, 2023

Agreed, it's work package and not team plan