Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 198

HOTSPOT -

At the end of stage 3, the service provider will be selected and the contract awarded. During stage 4, the Account Manager for the selected service provider will work with the Project Manager to complete the transition of the services to the selected service provider.

Hot Area:

    Correct Answer:

Discussion
ravi_aws

False ( selected service provider is in stage 4) , True |True, True | False, True | True, False | False, True | False, True

timedout

Should 4B not be false, as the Reporting Arrangements is to do with Checkpoint reports between the Team and PM? Page 541

pollon

1 - False, True 2 - True, True 3 - False, False 4 - False, True 5 - False (Benefit Tolerances are project-level tolerarance set at a Business Case Table 12.1), True