PRINCE2-Practitioner Exam - Question 198


HOTSPOT -

At the end of stage 3, the service provider will be selected and the contract awarded. During stage 4, the Account Manager for the selected service provider will work with the Project Manager to complete the transition of the services to the selected service provider.

Hot Area:

Show Answer
Correct Answer:

Discussion

3 comments
Sign in to comment
pollon
Aug 1, 2021

1 - False, True 2 - True, True 3 - False, False 4 - False, True 5 - False (Benefit Tolerances are project-level tolerarance set at a Business Case Table 12.1), True

timedout
Nov 3, 2021

Should 4B not be false, as the Reporting Arrangements is to do with Checkpoint reports between the Team and PM? Page 541

ravi_aws
Oct 6, 2023

False ( selected service provider is in stage 4) , True |True, True | False, True | True, False | False, True | False, True