PRINCE2-Practitioner Exam - Question 92


DRAG DROP -

STARTING UP A PROJECT -

Here are three actions carried out by the project manager during the 'starting up a project' process.

As part of which activity (A-F) should each action be carried out?

Choose only one activity for each action. Each activity can be used once, more than once, or not at all.

Select and Place:

Show Answer
Correct Answer:

Discussion

2 comments
Sign in to comment
ManikRoy
Dec 15, 2023

Acceptance criteria -- > Prepare outline Business Case as this is when PPD is created. (refer 14.4.4) Identify training Needs --> Design & Appoint the project management team. (refer 14.4.3) Document needs for confidentiality --> Select the project approach and assemble the project brief as this is when security constraints are considered. (refer 14.4.5)

ravi_aws
Oct 1, 2023

Confirming acceptance criteria for the project product is part of the Project Initiation Documentation (PID) in PRINCE2. Identify training needs is part of project approach confidential needs are part of business case.