PRINCE2-Practitioner Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Exam - Question 298


The 'training venue specifications' work package is now complete. All products have been approved by the Training Delivery Manager, as specified. The work package noted that the Training Delivery Manager should be sent the completed products. Therefore, the team manager sent the products to the Training Delivery

Manager without notifying the project manager, and updated the team plan to reflect that the work package has been delivered and no further work is required.

Has the team manager completed the required actions for the 'deliver a work package' activity, and why?

Show Answer
Correct Answer: D

The team manager has not completed the required actions for the 'deliver a work package' activity because the project manager should be notified in order to update the configuration item records. This ensures that all records are accurately maintained and that the project manager is aware of the completion of the work package.

Discussion

1 comment
Sign in to comment
ravi_awsOption: D
Oct 8, 2023

No, because the project manager should be notified in order to update the configuration item records