The 'training venue specifications' work package is now complete. All products have been approved by the Training Delivery Manager, as specified. The work package noted that the Training Delivery Manager should be sent the completed products. Therefore, the team manager sent the products to the Training Delivery
Manager without notifying the project manager, and updated the team plan to reflect that the work package has been delivered and no further work is required.
Has the team manager completed the required actions for the 'deliver a work package' activity, and why?