PRINCE2-Practitioner Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Exam - Question 133


DRAG DROP -

QUALITY -

Teams have been set up to develop different parts of the 'classroom-based training materials'.

Here are three activities related to managing quality.

Which role (A-F) should carry them out?

Choose only one for each activity. Each role can be used once, more than once, or not at all.

Select and Place:

Show Answer
Correct Answer:

Discussion

2 comments
Sign in to comment
ravi_aws
Oct 4, 2023

If the product meets requirements, the Project Manager will "sign off" the product, which confirms acceptance. So 1. Project Manager 2. Project Assurance 3. Project Manager

ravi_aws
Oct 4, 2023

For 3. I would rectify the answer to senior user.

ManikRoy
Oct 9, 2023

1. Project Manager 2. Project Assurance 3. Senior User