The external team manager for the 'e-learning course' has reviewed the quality register to ensure all quality activities have been completed. The 'e-learning course' has been approved and accreditation has been achieved. As a result, the team manager updated the work package to notify the project manager that it is complete, and updated the team plan.

Is this appropriate, and why?

    Correct Answer: A

    It is appropriate for the external team manager to update the work package and notify the project manager that the work has been completed. This is a crucial step to ensure that the project manager is aware of the completion status and the results of the quality activities. Confirmation that the e-learning course has been completed and accredited allows the project manager to proceed with the next steps in the project plan.

Discussion
ManikRoyOption: A

Refer 18.4.3 During 'Deliver A Work Package' the TM is responsible for updating both the 'Work package' & 'Team Plan' and also for activity 'Notify the project manager that the work package is complete'.

Merv49Option: B

correct

ravi_awsOption: A

The correct answer is A. Yes, because the project manager needs to receive confirmation that work has been completed and approved. In PRINCE2, once a work package is completed, the team manager is responsible for updating the work package status and notifying the project manager. This ensures that the project manager is aware of the progress and can update the stage plan and project plan accordingly. In this scenario, the team manager has appropriately updated the work package and team plan after ensuring all quality activities have been completed and the ‘e-learning course’ has been approved and accredited