Question 146

DRAG DROP -

INITIATING A PROJECT -

Here are three statements that were considered by the project management team during the 'initiating a project' process.

As part of which activity (A-F) should they FIRST be considered?

Choose only one activity for each statement. Each activity can be used once, more than once, or not at all.

Select and Place:

    Correct Answer:

Discussion
ManikRoy

Additional new requirements - Change control approach Combining Roles - Tailoring requirements Audit to check product - Quality management Approach

ravi_aws

The activity you’re describing is most closely related to “Prepare the change control approach”. This process involves setting up a system for managing changes to the project, such as new user requirements. These changes are only implemented if they are given a “must have” priority and approved by an executive.

ravi_aws

Others are correct

ManikRoy

Agreed.