Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 6

What is an off-specification?

    Correct Answer: C

    An off-specification is a type of issue that occurs when something that should be provided by the project is either not delivered or does not meet the required specifications. This could involve a missing product or a product that fails to conform to the agreed-upon quality standards.

Discussion
JasonbahrOption: C

off-specification is something that should be provided by the project, but currently is not (or is forecast not to be). It might be a missing product or a product not meeting its specifications. It is one type of issue.

peppeOption: C

issue is correct

a2d1fd1Option: C

An off-specification is something that is delivered but that isn’t right. E.g. Not fulfilling the quality specifications or perhaps not being delivered at all. A type of issue in PRINCE2.

faileruOption: C

c is the answer