PRINCE2-Foundation Exam - Question 6


What is an off-specification?

Show Answer
Correct Answer: C

An off-specification is a type of issue that occurs when something that should be provided by the project is either not delivered or does not meet the required specifications. This could involve a missing product or a product that fails to conform to the agreed-upon quality standards.

Discussion

6 comments
Sign in to comment
Jasonbahr
Apr 11, 2021

off-specification is something that should be provided by the project, but currently is not (or is forecast not to be). It might be a missing product or a product not meeting its specifications. It is one type of issue.

peppe
Oct 12, 2021

issue is correct

faileru
Aug 28, 2022

c is the answer

a2d1fd1Option: C
Apr 4, 2024

An off-specification is something that is delivered but that isn’t right. E.g. Not fulfilling the quality specifications or perhaps not being delivered at all. A type of issue in PRINCE2.

christianwillOption: C
Aug 26, 2024

Il s'agit d'un type de problème

3578791
Nov 1, 2024

First bullet: 4.6.4 Define key concepts related to the ‘issues’ practice: • issue (including types of issue: change, problem/concern, business opportunity, request for change, off-specification) (10.1, 10.2.2, 10.2.3) • project baseline (10.1) • change control (10.2.3)