According to the 'defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?
According to the 'defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?
According to the 'defined roles and responsibilities' principle in project management, three categories of stakeholder interest need to be represented in the project management team: Business, User, and Supplier. These three roles ensure that all critical aspects of the project are adequately addressed and managed.
Correct: Business, User and Supplier