PRINCE2-Foundation Exam - Question 175


Which statements about quality assurance and project assurance are CORRECT?

1. They are both independent of the project manager

2. They are both the responsibility of the project board

3. They are both independent from the project management team

4. They both assure that applicable standards are being used

Show Answer
Correct Answer: D

Quality assurance is independent of the project manager and focuses on ensuring that applicable standards are being used, which aligns with statements 1 and 4. Project assurance is part of the project board's responsibilities and is not completely independent from the project management team since it can involve review by the project board. Therefore, statements 2 and 3 are not entirely correct, making the correct answer 1 and 4.

Discussion

10 comments
Sign in to comment
johnzoidsOption: D
Jun 16, 2020

Its D (1,4)

sohrabianiOption: D
Oct 7, 2020

D is correct - Statement 3 is not right because they are not both independent from PMT - Project assurance is by PB which is part of PMT

peppeOption: D
Oct 20, 2021

D is correct

Prince_GemOption: C
Jun 5, 2020

Quality assurance are not part of Project management team

Mehan
Jan 14, 2021

D is the correct answer

MartijnRMOption: D
Jun 23, 2023

D IS RIGHT

RznNsrOption: D
Aug 19, 2023

D IS RIGHT

TesteurtestOption: D
Aug 21, 2023

Quality Assurance This is like Project Assurance but the focus is on Quality in the organization and not just quality related to the project. It is to make sure that the planned Quality activities are done. Provides a way to get an independent review of the Quality process; Checks to see that it complies with company Quality standards; and Ensures that Quality processes are in place. Project Assurance is the responsibility of the Project Board, while the Corporate or Programme Management is responsible for Quality Assurance. You can also say that the role Quality Assurance is outside the project management team while Project Assurance is within the project management team

Haranp12Option: D
Sep 30, 2023

Option 1 is definitely correct. And 4 is a better option than 3

HelgeFFMOption: D
Jan 12, 2024

I would also say D

TaiHOption: D
Jan 18, 2024

It is D