PRINCE2-Practitioner Exam - Question 17


MANAGING A STAGE BOUNDARY -

The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process.

Which action should the project manager undertake as part of the 'update the business case' activity?

Show Answer
Correct Answer: B

Updating the business case as part of 'managing a stage boundary' involves ensuring the project remains viable and justifiable. This includes revising the overall plan and resources to complete the project based on the actual progress, costs, and resource usage from the preceding stage. By doing this, it maintains the accuracy and relevance of the business case and ensures the project still aligns with its intended benefits and objectives. Therefore, the project manager should revise the overall plan and resources to complete the project, based on actuals from the stage 3 plan.

Discussion

7 comments
Sign in to comment
pollonOption: D
Aug 2, 2021

D - Update the business case Ref 19.4.3 - exam and review: whether any benefits reviews are required in the next management stage

timedout
Sep 6, 2021

Can you explain the rational behind D please Pollon? How does this relate to "Examine & Review" Thanks

windy1Option: B
Dec 7, 2021

I think it is B - based on 19.4.3

ravi_awsOption: B
Sep 30, 2023

B. Revise the overall plan and resources to complete the project, based on actuals from the stage 3 plan. Updating the business case involves ensuring that the project remains viable and justifiable given the current situation. This includes revising the overall plan and resource requirements based on the actual progress and costs incurred during the previous stage (in this case, stage 3). This revision helps ensure that the project is on track and that the business case remains valid for continuing with the project.

PieroBeOption: D
Jul 24, 2023

To my opinion it is D. According to Ref. 19.4.3: "Update the benefit management approach with the results from any benefit management actions undertaken during the (completed) management stage" as we can assume the fact pilot courses have been planned during closing stage 3 can trigger when the number of learners can be measured.

ChivasaOption: B
Oct 24, 2023

19.4.3 page 252

lovelifeysl_2021Option: C
Nov 16, 2021

I think it is C, what do you think?

ManikRoyOption: D
Oct 3, 2023

Option D seems to be the correct answer to me as this is updating business case with actions for benefit management review of next stage. Ref 19.4.3 in the manual , Examine and Review last point -- whether any benefits reviews are required in the next management stage