PRINCE2-Foundation Exam - Question 149


Which role represents the stakeholders who will operate the project's products after the project is complete?

Show Answer
Correct Answer: B

The Senior User represents the stakeholders who will operate the project's products after the project is complete. This role is responsible for ensuring that the project's products meet the needs of the end-users and that the products are delivered on time, within budget, and to the required quality standards.

Discussion

1 comment
Sign in to comment
Firey
Jul 23, 2024

The Senior User role is critical to the success of a project, as they represent the interests of the end-users who will ultimately be using the project's products or services. They work closely with the Project Manager to ensure that the project's goals align with the users' needs and requirements and are accountable for ensuring that the project's products are delivered on time, within budget, and to the desired quality standards.