PRINCE2-Practitioner Exam - Question 242


MANAGING PRODUCT ACTIVITY -

The product description for the 'marketing materials' states that the Sales Director will approve this product. It has been decided that there will be a presentation of the 'marketing materials' to the Sales Director in order to gain this approval.

In which activity should the team manager agree this approach?

Show Answer
Correct Answer: B

The team manager should agree on the approach during the 'Accept a work package' activity. This is when the team manager reviews and formally agrees to the details and conditions of the work package, including any requirements for approval and presentations to stakeholders like the Sales Director.

Discussion

1 comment
Sign in to comment
ravi_awsOption: B
Oct 7, 2023

B. Accept a work package