Which level of management sets the project level tolerances?
Which level of management sets the project level tolerances?
Corporate, programme management, or the customer is responsible for setting project-level tolerances. These entities are positioned above the project management team and ensure the overall direction and constraints within which the project operates. The tolerances they set guide the project board's actions and provide a framework for reporting and escalation. This ensures that the project aligns with strategic objectives and manages risks appropriately.
- setting tolerances • Corporate management: set project tolerances • project board: set stage tolerances • project manager agrees with team manager: set workpackages tolerances
Corporate, programme management or the customer sets the Project Level Tolerances.
The answer is Coporate/Programmme. Please you guys should do your research thoroughly before you mislead us. Some answers to the questions seen earlier were wrong.
Definitely C. ● Corporate, programme management or the customer This level sits above the project management team but will be responsible for commissioning the project, including identifying the executive and defining the project-level tolerances within which the project board will work. This information should, if possible, be recorded in the project mandate.
C is correct - Corporate, programme management or the customer set the project tolerances (mentioned in section 9.2.2 table 9.1 in the Plans theme and a few other places in the manual)
The correct answer is C. https://www.prince2primer.com/project-board-and-project-manager-prince2-controls/ As part of management by exception, corporate or programme management will have set project level tolerances. The project board need to agree stage level tolerances and optionally the project manager may set tolerances at work package level (although this may not need to be done at this point in time).
Answer should be C
C based on 12.2.4
The tolerances are set at one level above which they apply and are reported to this level. Corporate or Programme Management set the overall project tolerances. The Project Board is responsible for the project operating within these tolerances.
definitely, it is the corporate, who defines the tolerances level for the projects
CPC will set the Project tolerance so accordingly in case of exceeding those tolerances, the case be escalated to them PM will set the work package tolerance
Project board set stage tolerance, project manager set work package tolerance. Corporate program set project level tolerance. So many misleading on these exam practice
Correct Answer is C. 7.1 The four levels of management: Corporate, programme management or the customer This level sits above the project management team but will be responsible for commissioning the project, including identifying the executive and defining the project-level tolerances within which the project board will work. This information should, if possible, be recorded in the project mandate.
C is the right answer
It's C for me!
C is good
I totally agree this answer is wrong. It is Corporate/Programme that sets the Project tolerance.