PRINCE2-Foundation Exam - Question 168


Which is an objective of the 'initiating a project' process?

Show Answer
Correct Answer: A

The objective of the 'initiating a project' process is to ensure that baselines are established and controlled. This step is focused on laying the foundations for the project by setting up important structures and controls, such as establishing baselines which are essential for measuring the project's progress and performance.

Discussion

11 comments
Sign in to comment
sohrabianiOption: A
Oct 7, 2020

A is correct 100%

ShmellOption: A
Jun 30, 2020

The answer is actually A

ConstanzaOption: A
Jan 14, 2021

A is the correct answer (16.2-Objectives of the initiating a project)

ejaymacOption: A
Jul 10, 2020

Yes I agree A is correct

LenlenlenOption: A
Jul 25, 2020

should be A right?

RznNsrOption: A
Aug 19, 2023

A is the right answer. Dear admin, pls update the correct answer. its really confusing

Haranp12Option: A
Nov 10, 2023

A Refer section 16.2 - how baselines will be established and controlled

tarikaygul
Dec 21, 2023

definitely

peppeOption: A
Oct 17, 2021

NOT "CONTROLLED" BUT "HOW TO CONTROL"

Chucky2Option: A
Dec 2, 2022

A is correct

renzaOption: A
Feb 27, 2023

A is the right answer

RznNsrOption: A
Aug 19, 2023

The answer C is completely irrelevant and I don't know why this answer is blindly selected.