Which is an objective of the 'initiating a project' process?
Which is an objective of the 'initiating a project' process?
The objective of the 'initiating a project' process is to ensure that baselines are established and controlled. This step is focused on laying the foundations for the project by setting up important structures and controls, such as establishing baselines which are essential for measuring the project's progress and performance.
A is correct 100%
The answer is actually A
A is the correct answer (16.2-Objectives of the initiating a project)
should be A right?
Yes I agree A is correct
A is the right answer. Dear admin, pls update the correct answer. its really confusing
A Refer section 16.2 - how baselines will be established and controlled
definitely
The answer C is completely irrelevant and I don't know why this answer is blindly selected.
A is the right answer
A is correct
NOT "CONTROLLED" BUT "HOW TO CONTROL"