Question 246

CLOSING A PROJECT -

A product status account needs to be produced to identify if any concessions have been granted to support project closure at the end of stage 3 instead of stage

4.

During which activity of the 'closing a project' process should it be created?

    Correct Answer: B

    Prepare premature closure is specifically designed for situations where the project is closing earlier than originally planned, such as at the end of stage 3 instead of stage 4. This activity includes identifying the status of all products and ensuring that all necessary documentation, including any concessions granted, is completed to support the closure.

Discussion
mcesarlaraOption: B

Evaluate the products involves assessing the final products against the requirements to ensure they meet the expected standards and are fit for purpose. It does not specifically involve creating a product status account for closure purposes. Incorrect. Prepare premature closure is specifically for handling situations where the project is closed prematurely, which fits the scenario described (closing at the end of stage 3 instead of stage 4). It includes identifying the status of all products and ensuring all necessary documentation, including any concessions, is completed. Correct.

ravi_awsOption: C

C Evaluate the products is where the product status account should be created to identify any concessions supporting early closure. This confirms products are complete and supports the closure recommendation.