Question 118

Which should be provided by a project mandate?

    Correct Answer: A

    The project mandate should provide the terms of reference for the project. This includes the basic scope, objectives, and high-level requirements for the project, serving as the foundation for making further detailed plans.

Discussion
[Removed]Option: A

14.3 Context: The project mandate should provide the terms of reference for the project and should contain sufficient information to identify at least the prospective executive of the project board. The mandate is refined to develop the project brief.