Question 215

Which is a minimum requirement for applying the 'organization' theme?

    Correct Answer: B

    To delegate responsibility for managing product delivery to team managers is a minimum requirement for applying the 'organization' theme. The 'organization' theme in project management involves clearly defining the roles and responsibilities within the project. Delegating product delivery tasks to team managers is a fundamental aspect of ensuring that the project structure is well-organized and responsibilities are appropriately assigned.

Discussion
KANDUUR

7.2 correct