Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 101

During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?

    Correct Answer: C

    The correct answer is Quality Register. The Quality Register is used to capture, maintain, and report on quality management activities, including quality reviews and the creation of specialist products. It provides a comprehensive record of all quality checks and reviews conducted, ensuring that the quality criteria are met and documented accordingly.

Discussion
timedoutOption: C

Quality Register - 8.2 (page 152)

WikiVicksOption: B

I think B is more appropriate. A.4.2 states 'quality management activities carried out during the period'