During which process should release planning be done for the FIRST time?
During which process should release planning be done for the FIRST time?
Release planning should be done for the first time during the initiating a project process. During the initiation phase, the project goals, scope, and planning activities, including release planning, are defined. This sets the foundation for how the project will be executed and controlled.
Table 17.1
this is too much to be wrong!! Why I should have paid this crap!!
The answer is A
its answer A