PRINCE2-Foundation Exam - Question 248


Which is a minimum requirement for applying the ‘change’ theme?

Show Answer
Correct Answer: B

Documenting the format and contents of the issue register is a minimum requirement for applying the 'Change' theme in a project. The issue register serves as a repository for all change requests, ensuring that each request is properly recorded, tracked, and managed. This documentation is essential for maintaining control over changes and ensuring that their impact is thoroughly assessed and managed.