Which is an objective of the Starting up a Project process?

    Correct Answer: C

    The objective of the Starting up a Project process is to ensure that the basic information required for initiating a project is gathered and evaluated. This includes authorizing the Project Manager to proceed with the initiation stage, ensuring there is a clear understanding of the project's scope, and establishing if the project is viable and worth pursuing. Therefore, the correct option is to authorize the Project Manager to proceed with the initiation stage.

Discussion
Chucky2Option: A

A is correct The objective of starting up a project process is to ensure that there is a business justification for initiating the project. Sufficient information is available to define and confirm the scope of the project. The various ways that a project can be delivered are evaluated and a project approach is selected. Individuals are appointed who will undertake the work required in project initiation and all will take significant project management roles in the project.

peppeOption: C

The project plan is created during the initiating a project process and updated towards the end of each management stage during the managing a stage boundary process.

kal5

Referens for this answer appriciated

peppeOption: C

i would say C

dandandu1986Option: C

C. 14.2 individuals are appointed who will undertake the work required in project initiation and/or will take significant project management roles in the project

MrMooMooBeeOption: C

Authorisation of the initiation stages is Directing a Project so C isn't correct.

Risto83Option: A

A "Authorize" is in directing a project.

jj0097Option: C

C is good