Question 186

Which role is responsible for appointing the senior user in a project that is independent from a program?

    Correct Answer: B

    The executive is responsible for appointing the senior user in a project that is independent from a program. This responsibility falls under the executive's duty to design and appoint the project management team, ensuring that the team is adequately staffed with the necessary roles, including the senior user.

Discussion
MehanOption: B

PRINCE2 MAnual. Ref.C.2.1: In addition to the project board’s collective responsibilities, the executive will: design and appoint the project management team (in particular the project manager)

MEHREEN1985Option: B

7.2.1.2 The executive will then be responsible for designing and appointing the rest of the project management team, including the other members of the project board.

KianaOption: B

Senior user and senior suppliers both appointed by executive

GetRajOption: B

Appointed by the Executive

omandeOption: B

B is the correct answer.

peppeOption: B

B IS CORRECT Appointed by the Executive