PRINCE2-Foundation Exam - Question 186


Which role is responsible for appointing the senior user in a project that is independent from a program?

Show Answer
Correct Answer: B

The executive is responsible for appointing the senior user in a project that is independent from a program. This responsibility falls under the executive's duty to design and appoint the project management team, ensuring that the team is adequately staffed with the necessary roles, including the senior user.

Discussion

6 comments
Sign in to comment
MehanOption: B
Jan 16, 2021

PRINCE2 MAnual. Ref.C.2.1: In addition to the project board’s collective responsibilities, the executive will: design and appoint the project management team (in particular the project manager)

GetRajOption: B
Jul 4, 2020

Appointed by the Executive

KianaOption: B
Jul 31, 2020

Senior user and senior suppliers both appointed by executive

MEHREEN1985Option: B
Nov 18, 2022

7.2.1.2 The executive will then be responsible for designing and appointing the rest of the project management team, including the other members of the project board.

peppeOption: B
Oct 20, 2021

B IS CORRECT Appointed by the Executive

omandeOption: B
Nov 15, 2023

B is the correct answer.