What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
A Checkpoint Report is used by the Project Manager to review the status of Work Packages, including performance against cost tolerances. It provides detailed information on how the execution of the Work Package is progressing, making it the most relevant product for assessing cost tolerance.
A.4.2: A checkpoint report includes a Work Package Tolerance status, used to assess how the execution of the work package is performing against its tolerances (e.g. cost/time/scope actuals and forecast).