Question 55

Which is one of the six aspects of project performance that needs to be managed?

    Correct Answer: C

    One of the key aspects of project performance that needs to be managed is risk. Managing risks involves identifying potential threats to the successful completion of a project and taking steps to mitigate or manage them. Risk management is critical to ensuring that the project stays on track and meets its objectives despite uncertainties.

Discussion
renzaOption: C

6 variables to be controlled 1. Costs 2. Timescales 3. Quality 4. Scope 5. Risk 6. Benefits