PRINCE2-Practitioner Edition 6 Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Edition 6 Exam - Question 103


Which activity is responsible for updating the stage plan with actual during Controlling a Stage?

Show Answer
Correct Answer: B

The activity responsible for updating the stage plan with actuals during Controlling a Stage is 'Review work package status'. This is because reviewing work packages involves checking the progress made and recording actual progress against planned progress. This information is used to update the stage plan accurately.

Discussion

12 comments
Sign in to comment
xayay74894
xayay74894
Aug 11, 2021

Fig. 17.3 pag.221 Review work package status activity cleary updates the stage plan

johnzoids
johnzoids
Jul 17, 2020

update stage plan, is part of the review the management stage status, pg 223 fig 17.5

timedout
timedout
Sep 6, 2021

A is wrong by default as its missing the word "Management" B is correct "update" Review the management stage status "reviews", but I dont think it "updates"

MortenC
MortenCOption: B
Feb 14, 2023

17.4.2 page 221 4th bullet

johnzoids
johnzoids
Jul 17, 2020

or can be D, take corrective action pg 230 fig 17.9

Ciluba
Ciluba
Dec 23, 2020

Should be A. It is a recommended activity of review the management stage status.

xayay74894
xayay74894
Aug 11, 2021

Fig. 17.2 pag.219 Authorize a work package activity cleary updates the stage plan

MEHREEN1985
MEHREEN1985
Nov 30, 2022

C IS CORRECT REF: 17.4.1

MEHREEN1985
MEHREEN1985
Mar 17, 2023

sorry its B

PieroBe
PieroBeOption: B
Jul 25, 2023

Ref 17.4.2 (last bullet)

ravi_aws
ravi_aws
Oct 1, 2023

One of the key activities in the Controlling a Stage process is to review the status of the work packages . Work packages are the smallest units of work in PRINCE2, and they are assigned to team members to complete. By reviewing the status of the work packages, the project manager can gather information on the actual progress made and update the stage plan accordingly.

ManikRoy
ManikRoyOption: B
Oct 6, 2023

17.4.2 Review work package status Update the stage plan for the current management stage with actuals to date, forecasts and adjustments.

f41810f
f41810fOption: A
Dec 20, 2024

Coulc be A or B BUT Both activities can involve updating the Stage Plan, but "Review the Stage Status" has the broader and ultimate responsibility for ensuring that the Stage Plan is fully up-to-date, making it the correct answer in most PRINCE2 contexts. A Review of a work package MAY casue an update to the stage plan