Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 100

Which activity is responsible for updating the stage plan with actual during Controlling a Stage?

    Correct Answer: B

    The activity responsible for updating the stage plan with actuals during Controlling a Stage is 'Review work package status'. This is because reviewing work packages involves checking the progress made and recording actual progress against planned progress. This information is used to update the stage plan accurately.

Discussion
xayay74894Option: B

Fig. 17.3 pag.221 Review work package status activity cleary updates the stage plan

MortenCOption: B

17.4.2 page 221 4th bullet

timedoutOption: B

A is wrong by default as its missing the word "Management" B is correct "update" Review the management stage status "reviews", but I dont think it "updates"

johnzoidsOption: A

update stage plan, is part of the review the management stage status, pg 223 fig 17.5

ManikRoyOption: B

17.4.2 Review work package status Update the stage plan for the current management stage with actuals to date, forecasts and adjustments.

ravi_awsOption: B

One of the key activities in the Controlling a Stage process is to review the status of the work packages . Work packages are the smallest units of work in PRINCE2, and they are assigned to team members to complete. By reviewing the status of the work packages, the project manager can gather information on the actual progress made and update the stage plan accordingly.

PieroBeOption: B

Ref 17.4.2 (last bullet)

MEHREEN1985Option: C

C IS CORRECT REF: 17.4.1

MEHREEN1985

sorry its B

xayay74894Option: A

Fig. 17.2 pag.219 Authorize a work package activity cleary updates the stage plan

CilubaOption: A

Should be A. It is a recommended activity of review the management stage status.

johnzoidsOption: D

or can be D, take corrective action pg 230 fig 17.9