Which 2 statements should be recorded under the Timescale heading?
Which 2 statements should be recorded under the Timescale heading?
Under the Timescale heading, statements should indicate specific timeframes or durations related to the project's timeline. 'The contract with the selected service provider will be agreed during stage 3' specifies when an agreement will occur, and 'The transfer of equipment and staff is estimated to take six weeks' provides an estimated duration for a specific task within the project. These statements are directly related to time and scheduling, whereas the other options pertain more to benefits or conditional scenarios rather than concrete timeframes.
I believe B and E are correct. The end of Stage 4 is not a time scale. The stage 4 may take a couple of weeks, or month. Who knows...
Agreed...
B And D
Should be B & D
A) The contract with the selected service provider will be agreed during stage 3. E) The transfer of equipment and staff is estimated to take six weeks.
I think B & E, E because it it telling us the timeline for part of Stage 4. Whereas B is telling us the timeline of the expected benefits.
I think D is incorrect because the expected benefits will not be realised for 10 years "There is an expected saving of 20m over 10 years". Please correct me if wrong
A and E. B and D are benefits, C is a risk.
Agree, B, D seems more reasonable