PRINCE2-Practitioner Exam - Question 9


During stage 3, the project scope was extended to include a practice test for learners to take during the training course. The cost of this test will be included in the cost of the course.

The change to project scope was approved and the cost of ֲ£2,500 was paid for from the change budget. The project manager documented an increase of ֲ£2,500 in the project budget in the business case.

Is this an appropriate action, and why?

Show Answer
Correct Answer: C

No, because the use of the change budget means that the project budget does not need to be increased. The change budget is specifically allocated for unforeseen changes or modifications during the project. When a cost is covered by the change budget, it does not affect the overall project budget, which remains reserved for the original scope of the project.

Discussion

9 comments
Sign in to comment
georgio1974Option: C
Aug 2, 2023

agree it is C, the primary project budget is not affected as the change budget has been used

schrisOption: B
Oct 7, 2022

Does somebody know why it is not A, but B? Thank you in advance!

gregroboOption: A
Nov 28, 2022

i think this is A ? No ?

YanjuOption: A
Jan 15, 2023

It should be A

mogasserOption: C
Jul 2, 2023

Answer C (Unpopular objective answer/open for discussion) Ref. 9.3.1.5 "The budget should include: Cost of activities; Risk budget; Change budget; Cost tolerance" Ref. 11.3.6 " Including a change budget provides for a more realistic expectation of the overall costs/timeframe of the project."

YogenS
Jan 27, 2024

Hi, Can you explain please how and where to look for the reference -you provided? i.e. Ref. 9.3.1.5 and Ref. 11.3.6.... sorry for sounding to childish but I didn't get it

PieroBeOption: C
Jul 20, 2023

It is C as project budget includes change budget so no need to rise the project budget

ManikRoyOption: B
Sep 17, 2023

I think it should be option B as the project manager need to update the business case with updated cost at the end of each management stages. And I believe the change budget is part of the project budget!

ManikRoy
Oct 3, 2023

Sorry now get it, the primary project budget includes change budget, so the project budget remain unchanged.

ravi_awsOption: C
Oct 9, 2023

The change budget is specifically set aside for unforeseen changes that might occur during the project. When a change is approved and paid for from the change budget, it does not necessitate an increase in the project budget. The project budget is typically a forecast of the costs associated with the planned scope of the project, while the change budget is a reserve for unplanned changes.

ManikRoyOption: C
Dec 11, 2023

C. No, because the use of the change budget means that the project budget does not need to be increased.