Question 106

The Team Manager has received notification that the new hardware and software solution has been installed and completed, but there is a concern that it has not been approved by the appropriate people.

Which 2 actions should the Team Manager take to check that the completed products have been approved as required?

    Correct Answer: B, D

    To verify that the completed products have been approved as required, the Team Manager should first check the Product Descriptions to identify who should have approved the products. The Product Descriptions detail the quality and acceptance criteria, specifying the roles and responsibilities of the approvers. Secondly, the Team Manager should review the approval records specified in the Work Package. The Work Package includes the method of obtaining approval and the necessary documentation for this process. These steps ensure that the approval process was followed correctly and the appropriate individuals reviewed and sanctioned the products.

Discussion
ManikRoyOptions: BD

B & D 18.3 obtaining approval for completed products from the authorities identified in the product description. 18.4.2 check the work package and follow the method of obtaining and issuing approval records

ravi_awsOptions: BD

Based on the search results, the two actions that the Team Manager should take to check that the completed products have been approved as required are: B. Check the Product Descriptions to ascertain who should have approved the products. The Team Manager should review the Product Descriptions to determine who should have approved the completed products. The Product Descriptions outline the quality criteria and acceptance criteria for each product, as well as the roles and responsibilities of the approvers. By checking the Product Descriptions, the Team Manager can ensure that the appropriate people have reviewed and approved the products. D. Check the approval records as required in the Work Package. The Team Manager should review the approval records as specified in the Work Package. The Work Package should include information on the approval process for the completed products, including the names of the individuals or roles responsible for approving the products. By checking the approval records, the Team Manager can verify that the products have been approved as required.

PieroBeOptions: AE

This question seems to refer to the old syllabus, as per 6th ed. syllabus it should be A and E options. A options because in the WP we have the Approval Method paragraph that tells who will approve the WP's products and E options because the quality methods are in the PDs (attachment of the WP).