Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 79

What is the first task of product-based planning?

    Correct Answer: B

    The first task of product-based planning is to write the Project Product Description. This step is crucial as it defines what the project is meant to deliver, setting the foundation for all subsequent planning activities.

Discussion
ryou100Option: B

PRINCE2 uses the technique Product-Based planning to identify and analyze the planned products. The four steps in Product-Based Planning are: 1. Writing the Project Product Description 2. Creating the product breakdown structure 3. Writing the Product Description 4. Creating the Product Flow Diagram