Why are projects divided into management stages?

    Correct Answer: B

    Projects are divided into management stages to help the project board assess a project's ongoing viability. This division allows for regular review points at which the project's progress, risks, issues, and business case can be evaluated to ensure that the project remains justified and worth continuing. By doing so, it enables more effective decision-making and control over the project's direction and resources.