Question 90

While preparing the Quality Management Strategy, the Project Manager noticed that the corporate quality management system does not specifically cover project management.

Which option provides an appropriate way for the Project Manager proceed?

    Correct Answer: C

    To ensure a comprehensive approach to quality management in the project, it is essential to seek relevant organizational standards and involve key stakeholders in the development of the Quality Management Strategy. Facilitating a workshop with Project Assurance will help tailor the strategy to the project's specific needs and ensure alignment with broader organizational practices, even if the corporate quality management system does not explicitly cover project management. This approach promotes collaboration, thorough understanding, and commitment to quality standards throughout the project lifecycle.

Discussion
SantiagoAregentinaOption: C

It is "C"