Which process is used by the project board to respond to an exception report?
Which process is used by the project board to respond to an exception report?
The correct process used by the project board to respond to an exception report is 'Directing a project'. This process includes the activities and decisions related to managing the overall direction and guidance of the project, including responding to any exceptions or significant deviations from the project plan.
The Managing a Stage Boundary process is where the project board receives and reviews the exception report.